Upper floor coloured slab now set and ready for SIPs.

The brown upper floor slab has been poured. Tomorrow the bottom plates will be anchored down so the wall panels can be placed.

The brown upper floor slab has been poured. Tomorrow the bottom plates will be anchored down so the wall panels can be placed.

 

Simon is installing the stairs to the upper floor. Installation of the wall panels and then the roof trusses should finish the week off nicely.

Simon is installing the stairs to the upper floor. Installation of the wall panels and then the roof trusses should finish the week off nicely.